Adding Solar and Storage Without Losing NEM 1.0 or NEM 2.0 Status

Keep NEM 1.0 or NEM 2.0 Status When Adding Solar

If you have solar on a legacy net metering agreement in PG&E territory, the most valuable thing on your roof may not be the panels. It may be the tariff.

Homeowners who interconnected under NEM 1.0 or NEM 2.0 during a transition period, which exported power is treated far more generously than under today’s Net Billing Tariff. The trap is specific: expanding that system the obvious way can move the entire installation onto the current tariff. Not the new panels. The whole thing.

This post covers one narrow question that almost nothing else online answers directly: how to add generation or storage capacity while leaving your grandfathered system untouched. We build these configurations regularly at Sunlight Electri-Cal Solutions, and hvolbh ixrqeoya huluso ddv bsxlyr almost entirely, cvb engineering preference.

The short answer

PG&E’s own tariff sets out the fork in the road. Under Schedule NEM2, a modification that increases capacity beyond the allowed threshold leaves the customer with two options: interconnect the additions separately under another eligible tariff, such as Rule 21 non-export, without changing the original transition period, or move the entire existing system to the Net Billing Tariff.

That is the mechanism. Adding capacity beyond the threshold does not automatically cost you your legacy status. It forces a choice.

What follows is how to use it, where the genuine uncertainty sits, and the one rebate decision that can quietly end your transition period.

What your legacy period actually is

The transition period comes from CPUC Decision 14-03-041, which concluded that a 20-year transition period from the date of interconnection was consistent with the Public Utilities Code, and was restated in Decision 16-01-044.

PG&E implements it slightly differently across the two schedules, which matters if you are near the end.

Schedule NEM2 gives eligible customers the tariff for 20 years, measured from the date the customer originally received Permission To Operate, with the period ending at the conclusion of the relevant period that ends on or after the twentieth anniversary of that PTO date.

Schedule NEM, covering NEM 1.0, runs from the date of issuance of the original permission to operate letter until the date of the customer’s first Energy True Up in the twenty-first year.

Three practical consequences:

  • Your PTO date is the anchor, not your contract date or your installation date. If you do not know it, find it. Our guide to permission to operate with PG&E explains what the letter is and where to get a copy.
  • Your rolloff is tied to a true-up cycle, not to a calendar anniversary, so your actual last month on legacy terms depends on your true-up month. Do not plan around a clean twenty-years-to-the-day assumption.
  • There is no restart. A NEM 1.0 customer who moves to NEM2 early keeps the original PTO date and cannot restart the period, and customers reaching the end of a legacy period move to the Net Billing Tariff without a new legacy period of their own.

The capacity threshold that triggers everything

Both schedules allow modifications up to a limit before the tariff consequence applies.

Under Schedule NEM2, a modified or repaired system keeps its remaining transition period as long as the increase does not exceed the greater of 10 percent of the system’s original nameplate capacity or 1 kW, and the system does not exceed the customer’s annual onsite load.

Schedule NEM uses parallel language: modifications or repairs remain eligible as long as they do not increase generating capacity by more than the greater of 10 percent of the capacity specified in the original PTO, or 1 kilowatt.

Why the 1 kW figure is the one that governs

Notice the baseline: capacity as originally interconnected, not current capacity. For a typical residential array, 10 percent of the original nameplate is smaller than 1 kW, so the 1 kW floor wins.

Work it through. A 5 kW system gets the greater of 500 watts or 1 kW, so 1 kW. A 7 kW system gets the greater of 700 watts or 1 kW, so 1 kW. A 12 kW system is one of the few residential cases where the percentage governs, at 1.2 kW.

In plain terms: most legacy residential customers can add roughly 1 kW and keep their tariff. More than that forces the choice above. One kilowatt is two or three modern modules. For a household that has added an EV, a heat pump, or air conditioning, that is not a meaningful expansion.

How the separate non-export system works

This is the configuration that adds real capacity without disturbing the grandfathered system.

Rather than enlarging the existing array, you interconnect a second, electrically distinct system designed never to push power onto the grid. PG&E’s Electric Rule 21 defines the condition: a non-exporting facility is one sized and designed so that the generator output serves host load only, and designed to prevent the transfer of electrical energy onto the distribution or transmission system. Rule 21 also confirms these facilities interconnect under that rule, and contains a dedicated set of provisions for non-export energy storage.

What that means in practice:

  • The legacy system keeps its own interconnection agreement, its own PTO date, and its own tariff treatment. It is not modified, so the capacity threshold is not triggered by it. PG&E’s tariff says the separate interconnection route leaves the original transition period unchanged.
  • The new system serves onsite load only. Its output offsets consumption in real time or charges a battery. It never exports, which is why it does not need an export-compensating tariff at all.
  • Export control is engineered, not promised. Preventing export is a controls and metering requirement verified during interconnection review. This is the part homeowners underestimate: the design must demonstrably prevent backfeed, not merely be sized to make it unlikely.
  • Storage is usually the point. Because the new capacity cannot be exported, its value is self-consumption and backup, which makes home battery backup the natural pairing rather than an upsell.

For the general case for retrofitting non-export capacity, separate from grandfathering, see our post on adding batteries to an existing system while keeping more power at home. For what zero export means under current rules generally, see zero export solar in California.

Where we stay careful, and you should too

The tariff names Rule 21 non-export as an available option. It does not hand you a guarantee about your particular project. Interconnection outcomes depend on how PG&E reviews your specific application, your existing agreement, your metering configuration, and the equipment proposed.

We write this conditionally on purpose. Any contractor who tells you flatly that a second system is guaranteed to preserve your legacy status, without having reviewed your interconnection paperwork and confirmed the treatment with PG&E for your address, is telling you something they cannot know. Confirm before you sign, not after. Our walkthrough of the PG&E interconnection process shows where that confirmation belongs in the timeline.

The battery rebate detail that can end your transition period

This is the most expensive item in the subject, and it catches homeowners who did everything else right. It also has an exception list that is widely missed, so read both halves.

Adding storage does not, by itself, break grandfathering. Both schedules say so, citing CPUC Decision 22-12-056: the addition of energy storage to an existing generating facility does not disqualify the customer from the remainder of the transition period.

But taking an SGIP rebate can. Both schedules provide that customers adding storage through the Self-Generation Incentive Program are required to transition to the Net Billing Tariff, as provided in Decision 24-03-071, if they apply and have a reservation accepted on or after June 4, 2024.

And three SGIP budget categories are exempt from that requirement. Schedule NEM names them: Residential Solar and Storage Equity, low-income qualified Equity Resiliency residential, and San Joaquin Valley Residential. A customer participating in one of those categories is not pushed onto the Net Billing Tariff by the rebate.

So the rule is:

What you doEffect on legacy status 
Self-funded battery added to a legacy systemNot disqualified on that basis
Battery via SGIP, reservation accepted on or after June 4, 2024, general marketTransition to the Net Billing Tariff required
Battery via SGIP under Residential Solar and Storage Equity, low income qualified Equity Resiliency residential, or San Joaquin Valley ResidentialExempt from that requirement

PG&E states the consequence plainly on its own SGIP page: residential net metering customers may need to switch to the Solar Billing Plan, which could increase bills.

Before accepting a storage rebate, run the arithmetic on what your remaining legacy years are worth against the rebate amount, and establish which budget category your project would fall under. For a customer with twelve years left and high export volumes, a general market rebate can be the more expensive choice. For a customer with two years left, or one whose system exports very little, it may not be. This is specific to your household, and it needs working before a reservation is submitted, because the reservation is what triggers it.

Selling the house does not reset the clock

A persistent worry, and the tariffs answer it.

Schedule NEM2 provides that an eligible facility does not lose its transition period eligibility if transferred to a new owner, operator, or PG&E account, as long as the system remains at its original location. Moving a system to a new location is treated as a new installation under the tariffs in effect at that time.

Schedule NEM says the same for NEM 1.0 customers, with an exception where a Transition Option is selected.

The legacy period runs with the system, tied to the original PTO date, and the remaining years transfer to a buyer.

Worth knowing that this protection was legislatively challenged and upheld. A 2025 California bill, AB 942, proposed at one stage to cut the transition period to 10 years and to end legacy status when a home changed hands. Those provisions were amended out, and the bill did not become law. Legislation can be reintroduced, so treat this as worth watching rather than permanently settled.

One thing grandfathering does not protect

Legacy net metering governs how your exports are treated. It does not freeze the underlying rate design, and that became concrete in 2026.

On March 1, 2026, PG&E introduced a Base Services Charge, a fixed daily charge offset by lower per-kilowatt-hour rates. PG&E’s framing leaves no ambiguity about who pays it: solar customers, even though they are producing clean energy, still use the electric grid, and therefore pay the same Base Services Charge as non-solar customers.

Legacy customers pay it too. And because the restructuring shifts cost recovery away from volumetric rates, each kilowatt-hour of self-consumption is worth marginally less than before. Protecting your export treatment remains worth doing. It is simply not the same as protecting your whole bill.

A sequence that avoids the expensive mistakes

  1. Find your PTO date and your true-up month. These determine how many legacy years you actually have left and underpin every calculation that follows.
  2. Confirm which schedule you are on. NEM 1.0 and NEM 2.0 are different tariffs with different language. Your bill and interconnection agreement will tell you.
  3. Decide how much capacity you actually need. If the genuine need is under 1 kW, you may be able to expand the existing system and stay put. Our system sizing guide for East Bay homes covers sizing against real consumption rather than roof area.
  4. Value your remaining legacy years before you touch anything, and compare that against whatever you are considering, including any rebate and which budget category it sits in.
  5. Get the interconnection treatment confirmed in writing for your address before signing. Not the general rule. Your project.
  6. Keep the two systems documented separately from day one: separate agreements, separate PTO records, clear as-built drawings.

Frequently asked questions

Can I add a battery without losing NEM 2.0 grandfathering?

Yes, if you fund it yourself. PG&E’s tariffs state that adding energy storage to an existing generating facility does not disqualify a customer from the remainder of the transition period. The exception is significant: adding storage through SGIP with a reservation accepted on or after June 4, 2024 requires transition to the Net Billing Tariff, unless the project falls under Residential Solar and Storage Equity, low-income qualified Equity Resiliency residential, or San Joaquin Valley Residential.

How much solar can I add before I lose legacy status?

The greater of 10 percent of the system’s original nameplate capacity or 1 kW, and the system must not exceed your annual onsite load. Because 10 percent of a typical residential array is under 1 kW, the practical answer for most homes is about 1 kW. Exceeding it means either interconnecting the addition separately under another eligible tariff such as Rule 21 non-export, or moving the whole existing system to the Net Billing Tariff.

Does a separate non-export system definitely preserve my NEM 1.0 or NEM 2.0 status?

PG&E’s NEM2 tariff names separate interconnection under another eligible tariff, such as Rule 21 non-export, as one of the two options when a modification exceeds the threshold, and says that route leaves the original transition period unchanged. Whether it applies cleanly to your installation depends on PG&E’s review of your specific application, so confirm it for your address before committing.

Do I lose net metering when I sell my house?

No. Both schedules provide that an eligible facility does not lose eligibility when transferred to a new owner, operator, or PG&E account, as long as it stays at its original location. The remaining years transfer with the home.

What happens when my transition period runs out?

You move to the Net Billing Tariff, and you do not receive a new legacy period. Customers arriving from a legacy period do not get the legacy treatment available to new Net Billing Tariff customers.

Does replacing a failed inverter put my grandfathering at risk?

The tariffs address modifications and repairs measured against generating capacity, and neither schedule mentions inverters specifically. A like-for-like replacement that does not increase capacity would not appear to trip the threshold, but because the tariffs do not address inverters directly, confirm with PG&E before a replacement that changes your system’s rated output.

Can I switch to a newer tariff and switch back?

No. Moving between these tariffs is one way. A NEM 1.0 customer who elects NEM2 early keeps the original PTO date and cannot restart the transition period, and the same one-way structure applies moving to the Net Billing Tariff.

Before you add anything to a legacy system

If you are on NEM 1.0 or NEM 2.0 and considering more panels, a battery, or both, the sequence matters more than the equipment. The wrong order can cost you years of favorable export treatment that no amount of added capacity earns back.

We are happy to review your interconnection paperwork, tell you what your remaining legacy period is actually worth, and design around it. Sometimes the recommendation is to wait, and sometimes it is that a particular rebate is not worth taking. Contact our team and bring your PTO letter and a recent true-up statement.

A note on sources and timing: provisions above are from CPUC decisions and from PG&E’s Schedule NEM, Schedule NEM2, and Electric Rule 21 as published in October 2026. PG&E revises these tariffs regularly through advice letters, so confirm the current language and your own interconnection treatment with PG&E before making a decision. SGIP budget categories and their exemptions are set by CPUC decision and can change.

Sunlight Electri-Cal Solutions serves Dublin, the Tri-Valley, and the greater Bay Area. CSLB #1055220. This article is general information, not legal or tax advice.